  • Harvil Road – overnight road closures

    Monday April 28, 9:30 pm to Saturday May 17, 6:00 am

    Harvil Road – overnight road closures

    Between 17 February and 17 March, the  manufacturer of welded parts of the new Harvil Road Bridge, carried out some planned surveys. They now require additional time to continue the activity on the bridge.
    To ensure the safety of both the operatives and rail users, the work will take place when no trains are operating on the Chiltern Line. Due to the need for
    this rail possession, these works can only be done at nighttime.

    From 28 April to 17 May 2025 Harvil Road will be closed overnight to allow the following activities to be carried out safely:
    • testing of welded parts of the new Harvil Road bridge,
    • snagging works along the footpath on Harvil Road to repair paving
    defects and cracks.
    These activities are non-intrusive, with a minimal noise level expected
    ensuring that any disruption is kept to a minimum.

    HS2 apologise for any disruption or inconvenience these works may cause.  Please find further information here