News

    • Breakspear Road South Closure Update

      August 17, 2019

      Update: Breakspear Road South reopens to motorists from 8pm Friday 16 August until 6am on Saturday 31 August

      The first phase of the works at Breakspear Road South has been completed as planned. The road will be open to traffic from 8pm on Friday 16 August until 6am on Saturday 31 August. There will still be a lane ... Read more

    • TBM power supply trial hole update

      August 8, 2019

      Trial holes have been planned to take place along the length of the proposed TBM power supply route starting in Rayners Lane and moving westwards to West Ruislip. The trial holes, which are around 1m square in size, should only take a day to complete.

      HS2 have said that work will start on 12 August and is expected to last for two weeks.

      During the week beginning ... Read more

    • Shopping Around Exhibition

      August 2, 2019

      Shopping Around – the growth of shops in our area

      An exhibition by
      Ruislip, Northwood & Eastcote Local History Society
      at
      Manor Farm House, Ruislip

      August 2nd to September 12th

      Wednesday to Friday 12.00 to 3.00pm
      Saturday and Sunday 12.00 to 4.00pm

      Read more
    • Draft Statement of Gambling Principles

      July 24, 2019

      Draft Statement of Gambling Principles 2019 – 2022

      The Gambling Act 2005

      The Council has reviewed its Statement of Gambling Principles and has made some minor amendments.

      The revised policy 2019 – 2022 is scheduled to come into force on 21st November 2019 and is available to view on the Hillingdon website – click here

      Should you wish to make any comments on the revised ... Read more

    • Burst Water Main

      July 4, 2019

      High Road Eastcote is currently closed due to a burst water main.

      We have been advised that the earliest this will re-open is Sunday.

      Diversions are in place but allow extra time for your journey.

      Read more
    • HS2 Power Supply Leaflet

      June 21, 2019

      HS2 and UKPN have recently signed a contract for UKPN to provide the power supply, which is necessary to run the equipment HS2 need to bore the tunnel from West Ruislip back to Old Oak Common. In order to supply this power for the Tunnel Boring Machines, UKPN will need to lay a power cable from their Sub-station in Rayners Lane to West Ruislip.

      UKPN is ... Read more

    • RAF Northolt consultation feedback

      June 18, 2019

      ERA was involved in a recent consultation by RAF Northolt and we have received this feedback: rafnortholt jun 2019

      Read more
    • Congratulations to Northwood Hills Residents’ Association

      June 4, 2019 On 2nd June, Buckingham Palace announced that Northwood Hills Residents’ Association had been awarded The Queen’s Award for Voluntary Service.”  This is the highest award given to local volunteer groups across the UK to recognise outstanding work done in their own communities. Read more
    • HS2 Update

      May 31, 2019

      HS2 have now set up a page on their Commonplace website dedicated to the TBM Power supply:  click here – you can sign up to receve weekly updates at the bottom of that page.

      Read more
    • HS2 Breakspear Road – UPDATED

      May 31, 2019

      Further to this post from last week, HS2 have now written to say that the closure of Breakspear Road South has been postponed to the summer holidays (July 19).

      Many thanks to all who were involved in this campaign.

      Please note that HS2 have stated that it may take several days to organise the removal of the road ... Read more