Breakspear Road South Closure Update

Update: Breakspear Road South reopens to motorists from 8pm Friday 16 August until 6am on Saturday 31 August

The first phase of the works at Breakspear Road South has been completed as planned. The road will be open to traffic from 8pm on Friday 16 August until 6am on Saturday 31 August. There will still be a lane closure, with traffic flowing in both directions controlled by temporary traffic lights.

A map of the lane closure is below.

As planned following this lane closure there will be a further full road closure for 15 days, starting Saturday 31 August at 6am to Saturday 14 September 2019 at 8pm.

For more details contact the HS2 Helpdesk on 08081 434 434

There is also a dedicated Breakspear Road South Closure page on the HS2 at Hillingdon website, which also has the HS2 Breakspear Road South closure Question & Answer document.